← Back to guides
GuideAssessment guide

How should an existing building ventilation system be assessed?

A practical method for combining current room use, drawings, BMS data, airflow measurements and occupant evidence into a defensible ventilation assessment.

Existing building problems are rarely solved by one table lookup or one sensor. The useful question is whether the current building use, system operation and measured air path still match the ventilation basis.

01

The practical answer

Start with the current enclosure use and occupancy, reconstruct the intended ventilation path, verify how the system actually operates, then use measurements to test the assumptions. Do not begin with a CO₂ threshold or a fan replacement.

The same building can drift away from its original ventilation basis through fit-outs, occupancy changes, blocked openings, control changes and deferred commissioning.

A good assessment uses drawings and design information as one source of evidence, but it also checks current room use, terminal settings, BMS sequences, air paths and representative measurements.

The final output should state what is known, what is assumed, what was measured and what changes are required. That is more useful than a generic ‘complies/does not comply’ statement unsupported by the real system condition.

02

When this guide is useful

Use this guide when
  • Occupants report stuffiness, odours or recurring high CO₂.
  • A room or tenancy use has changed since the original design.
  • Mechanical drawings exist but current airflow performance is uncertain.
  • A natural-ventilation strategy may have been compromised by alterations.
  • The owner wants to know whether balancing, controls or capital upgrades are really needed.
Do not use it to
  • Treating CO₂ as a universal pass/fail metric.
  • Replacing detailed HVAC design where a new system is being created.
  • Ignoring fire-mode and microbial-control interfaces when plant is modified.
  • Assuming an old commissioning report still represents the current building.
03

A six-step existing-building ventilation assessment

Follow the building from use to air path to operation to measurement. Each step should either confirm the basis or expose an uncertainty worth testing.

01

Define the current building use

Record actual room functions, occupancy density, schedules and recent fit-outs. Do not rely on superseded room names.

02

Reconstruct the intended ventilation strategy

Identify mechanical supply, exhaust, transfer air, natural openings and any mixed-mode arrangement.

03

Review the system operation

Check fan schedules, VAV minima, dampers, demand-control logic, BMS overrides and actual occupied-hour operation.

04

Inspect the physical air path

Look for blocked intakes, altered doors, partition changes, obstructed louvres, dirty components and disconnected transfer paths.

05

Measure representative performance

Use airflow, pressure, CO₂ or other contaminant data where it will test a specific uncertainty under representative conditions.

06

Define and verify the remedy

Choose balancing, controls, operating, natural-opening or capacity changes and recommission the affected system.

04

Detailed engineering examples

These cases show how the framework changes a real engineering decision. They are deliberately written around uncertainty, options and evidence rather than one universal answer.

Case study 1 · Office complaint investigation

One floor has high afternoon CO₂ after a tenancy expansion

01
The decisionIs the AHU undersized, or is the problem local to air distribution and controls?
Project context

A commercial office adds workstations without changing the central HVAC plant. Portable sensors show high afternoon CO₂ on one floor, while other floors appear acceptable.

What makes the decision difficult

  • The central AHU serves several floors.
  • The affected floor has new meeting rooms and changed VAV zoning.
  • The sensor data are not linked to occupancy or terminal airflow.

How the guide should be applied

  1. Confirm the current floor occupancy and room uses.
  2. Review VAV minimums and the central outdoor-air strategy.
  3. Trend CO₂ with occupancy and measure selected terminal airflows.
  4. Compare the affected floor with a control floor before proposing central plant replacement.
Practical outcome

The assessment may reveal a local balancing or control problem rather than inadequate central plant capacity. The project spends money where the evidence points, not where the loudest complaint points.

Case study 2 · Natural ventilation review

Warehouse refurbishment blocks the original louvre path

02
The decisionDoes the original natural-ventilation basis still describe the building?
Project context

A warehouse historically relied on wall louvres and large open areas. New racking and enclosed rooms change the internal airflow path.

What makes the decision difficult

  • The original design calculations are unavailable.
  • Some louvres are obstructed by storage.
  • New rooms have no direct external openings.

How the guide should be applied

  1. Map the current enclosures and permanent openings.
  2. Separate gross opening dimensions from effective free area.
  3. Identify zones that no longer have a dependable cross-ventilation path.
  4. Use mechanical ventilation selectively where the natural strategy is no longer robust.
Practical outcome

The result is a documented mixed-mode solution instead of an unsupported assumption that the whole warehouse remains naturally ventilated.

Case study 3 · Car park controls

CO alarms, noisy fans and uncertain BMS logic

03
The decisionIs the problem fan capacity, air distribution, make-up air or monitoring?
Project context

A basement car park has recurring alarms and complaints about fan operation. The owner assumes the exhaust fans are undersized.

What makes the decision difficult

  • Sensor calibration records are incomplete.
  • Security screens changed make-up-air paths.
  • The BMS sequence has been modified several times.

How the guide should be applied

  1. Map the car park zones, sensors, fan system and make-up-air paths.
  2. Verify monitoring operation before treating every alarm as a ventilation-capacity failure.
  3. Trend contaminant levels against fan speed and operating conditions.
  4. Investigate stagnant zones and blocked air paths before changing fan size.
Practical outcome

The final remedy may be controls, sensor, distribution or make-up-air work rather than major fan replacement.

05

Common traps

Starting with a sensor threshold

Measurements should answer a defined system question, not replace the assessment method.

Trusting drawings without field verification

Fit-outs and controls often drift away from the original documentation.

Measuring total fan flow only

Distribution and terminal control can leave individual zones under-ventilated.

Ignoring operating schedules

Adequate design capacity is irrelevant if the system is off or at turndown during occupancy.

Fixing symptoms before defining the cause

More fan speed can worsen noise, pressure and energy use without solving the actual problem.

06

Evidence to gather before deciding

Current room-use and occupancy schedule

Mechanical drawings and airflow schedules

Natural ventilation opening information

BMS sequences, alarms and trends

VAV and terminal settings

Airflow and pressure measurements

CO₂ or contaminant trends with context

Commissioning and balancing records

Recent fit-outs and building alterations

Occupant complaint pattern

07

Useful engineering outputs

1

Ventilation basis map

A concise record of how each relevant zone is intended to receive and discharge air.

2

Evidence summary

Drawings, operating data, measurements and uncertainties organized around the actual ventilation questions.

3

Remediation and recommissioning plan

Specific control, balancing, opening or capacity changes with verification steps.